Investor Bayer Pharmaceuticals
Project Name Transformation Center Installation
Location Istanbul / Turkey
Contract Start Date 2015
Work End Date 2015
Project Status Done

Services Provided Within the Scope of the Project

      • Medium Voltage Power Distribution (Transformer Substation)
      • Testing and Commissioning
With the Transformer Center Installation project completed in 2015 at the facility of Bayer Pharmaceuticals in Istanbul, the factory's energy infrastructure was strengthened and safe and uninterrupted power was provided.
In the project, the installation of a 34.5/0.4 kV transformer center, medium voltage cells, distribution boards and cabling works were carried out. The system is designed to guarantee production continuity and operational safety.