Investor | Okan University |
---|---|
Project Name | Transformer Center Installation |
Location | Istanbul / Turkey |
Contract Start Date | 2006 |
Completion Date | 2006 |
Project Status | Completed |
For Okan University Tepeören Campus in Istanbul, a 34.5/0.4kV 2x1600 kVA transformer facility was installed in 2006. Within the project scope, medium voltage power distribution (transformer center installation), mounting of low voltage distribution panels, cable trays and cabling works were completed. All systems were tested and commissioned.