Investor | Piyalepaşa Istanbul |
---|---|
Project Name | Transformer Substation Installation |
Location | Istanbul / Turkey |
Contract Start Date | 2017 |
Completion Date | 2017 |
Project Status | Completed |
The "Transformer Substation Installation" project completed in 2017 for Piyalepaşa Istanbul provided a comprehensive energy infrastructure solution. The project included the installation of a total of 7 dry-type transformers (3x1000kVA, 1x1250kVA, and 3x1600kVA capacity) and 43 medium voltage (MV) cells. Supported by the installation of 10,000 meters of MV cable, the project also established low voltage distribution panels and cable channels, creating a modern energy distribution network. All systems were successfully tested and commissioned, ensuring Piyalepaşa Istanbul a reliable and efficient electrical infrastructure.